Maintenance Notification - October

Please review the following information for scheduled maintenance details:

UPS Maintenance:

Monday, Oct 10th, 8:00 AM - 5:00 PM PDT (GMT-7) 
Tuesday, Oct 11th 5:00 AM - 5:00 PM PDT (GMT-7)

Customer Impact:

There should be no impact to the power in the facility and no down time is expected.
This notice is for advisory purposes only.

Maintenance Details:

The maintenance schedule will be completed in 2 phases.

Monday Oct 10th  - Preventive Maintenance performed on UPS 1 and 2.
Tuesday Oct 10th  - Preventive Maintenance performed on UPS 3 and 4.

---------------------------------------------------------------

Generator Run:

Thursday, Oct 20th 7:00 PM - Friday, Oct 21st 6:00 AM PDT (GMT-7)

Customer Impact:

There should be no impact to the power in the facility and no down time is expected.
This notice is for advisory purposes only.

Maintenance Details:

We will also be performing our quarterly generator run Thursday, Oct 20th, 2011 from 7:00 pm PDT to 6:00 am PDT Oct 21st, the expected time on generator should be approximately 11 hour.

Quarterly Generator Run (test) required to ensure contingent power in case of an outage.

Inquiries:

If there are any additional questions before, during, or following the maintenance, please direct them to the ServePath Support Center via phone or open a case online at http://my.ServePath.comhttp://my.ColoServe.com or http://my.gogrid.com.

Thank You for your continuing support with GoGrid.

Sincerely,

GoGrid Data Center Team