GoGrid Maintenance Notice

Please review the following information for scheduled maintenance details:

GoGrid Datacenter Maintenance Window:
Monday, April 2 2012 8:00 - 17:00 PDT (GMT -7)
Tuesday, April 3 2012 8:00 - 17:00 PDT (GMT -7)

Customer Impact:
There should be no impact to the power in the facility and no down time is expected.
This notice is for advisory purposes only.

Data Center:
US-West-1

Maintenance Details:
There will be a quarterly preventive maintenance will be performed on UPS 1, 2, 3 and 4
UPS maintenance is required to continue to provide consistent, uninterrupted power to our customers

Inquiries:
Customers who have additional questions before or after the maintenance are requested to contact the GoGrid Support Center via the portal or by phone (1-877-946-4743 or +1-415-869-7444).

Sincerely,

GoGrid Data Center Team