Friday, April 19, 2013

GoGrid Power Infrastructure Maintenance - 2013-04-21


GoGrid Power Infrastructure Maintenance:
Sunday, April 21, 2013 - Monday, April 22, 2013

Customer Impact:
This notice is for advisory purposes only. Customers should not experience any issues.

Data Center:
US-EAST1

Maintenance Details:
GoGrid Engineers are performing switchboard maintenance in US-East1 data center.  This will require short power transfers to generators.  The generator mode period will be short and comparable to the normal monthly generator tests.

Inquiries:
Customers who have additional questions before, during, or after the maintenance are requested to contact the GoGrid Support Center via the portal my.gogrid.com, by phone (1-877-946-4743 or +1-415-869-7444).