Monday, April 22, 2013

GoGrid Power Infrastructure Maintenance - 2013-04-23


GoGrid Power Infrastructure Maintenance:
Tuesday, April 23, 2013

Customer Impact:
This notice is for advisory purposes only. No customer impact is expected.

Data Center:
US-WEST1

Maintenance Details:
GoGrid Engineers are performing switchboard maintenance in US-WEST1 data center.  This will require short power transfers to generators.  The generator mode period will be short and comparable to the normal monthly generator tests.

Inquiries:
Customers who have additional questions before, during, or after the maintenance are requested to contact the GoGrid Support Center via the portal my.gogrid.com, by phone (1-877-946-4743 or +1-415-869-7444).